The proposal put forth by Kenyan President William Ruto to develop 200,000 housing units each year is facing financial hurdles, causing project stoppages, budget excesses, and postponements, as highlighted by a report from lawmakers.

The affordable housing project pipeline, estimated at 1.76 trillion shillings ($13.6 billion), has already spent 198 billion shillings since its launch in 2023, according to data from the Parliamentary Budget Office.

As of the end of June, 176 projects – accounting for 15% of ongoing construction – had ground to a halt due to delays in payments to contractors, the report states. These housing developments are projected to reach completion by 2032.

“This financial shortfall is likely to expose the affordable housing initiative to deeper fiscal and operational challenges, as it will find it hard to maintain a smooth implementation process across its entire portfolio,” remarked the agency advising lawmakers on budget issues.

ADVERTISEMENT

CONTINUE READING BELOW

Challenges encompass “project delays stemming from insufficient funding, budget overruns induced by penalties for tardy contractor payments, and escalating construction expenses due to prolonged timelines.”

The funding gap poses a substantial threat to Ruto’s objectives for developing apartments, hostels, slum enhancements, and marketplaces—initiatives critical to enhancing his support as he seeks re-election next year.

A funding deficit of 118.3 billion shillings represents just over half of the required amount for the current fiscal year. This comes despite an unpopular 3% housing levy on incomes, which has generated 205.7 billion shillings since its introduction in 2023, as reported.

ADVERTISEMENT:

CONTINUE READING BELOW

Officials are encouraged to allocate funds from the housing levy specifically for these initiatives and to prioritize those nearing completion to generate further revenue through sales, according to the budget office.

The agency also warned against shifting energy and petroleum sector projects worth 45.9 billion shillings from direct budget financing to the newly formed National Infrastructure Fund. Such a transition could delay these projects as they might need new approvals from external financiers, fresh assessments of commercial viability, and adjustments to existing agreements.

Given that the fund is in its infancy, “these projects may encounter delays while awaiting evaluation, potentially resulting in cost overruns due to penalties for overdue contractor payments and commitment fees from approved but undisbursed development financing from lending entities,” the report indicated.